BUSINESS PLATFORM - ENERGY, REsSOURCES & INFRASTRUCTURE
In 2023, Australia will become the first country in the world to power up one of General Electric’s (“GE”) 320MW 9F.05 dual fuel hydrogen and natural gas turbines for grid electricity.
Clough was awarded the engineering,
procurement and construction (“EPC”)
scope for Energy Australia’s Tallawarra
Stage B project in May 2021.
This project, located in Yallah, New South
Wales (“NSW”), is set to be Australia’s first
hydrogen and gas capable power station
and Australia’s first net zero emissions
hydrogen and gas capable power plant,
with direct carbon emissions from the
project offset over its operational life.
Tallawarra B project will provide over
300MW of dispatchable capacity for
NSW when commissioned in 2024 and
coincides with the retirement of the Liddell
1.6GW coal-fired power plant. The plant
will be ready to start generating electricity
for 150,000 homes with only 30 minutes
notice and addresses the need for fast-start
flexible capacity to complement renewables
coming into the system.
Energy Australia, through its Tallawarra B
project, is setting a new benchmark for
how gas generators can reach net zero
emissions as it will use green hydrogen and
offset residual emissions.
The project team reached a major milestone
with the arrival of the GE 320MW 9F.05 dual
fuel hydrogen and natural gas turbine in
Port Kembla.
The turbine is one of the project’s main
mechanical equipment items and the first of
three major heavy lift items to arrive in
the country. Weighing in at approximately
372 tonnes with a transport envelope of
11m x 5m x 5m, the turbine was exported
from Greenville, South Carolina, USA,
and spent over a month at sea en route
to Australia.
The turbine achieved the next stage of its
journey when it was transported overland,
from Port Kembla to the project site in Yallah.
This journey, by itself, was an impressive feat.
Clough engaged the heavy lift transportation
specialist, Lampson, to get the turbine to
site safely. It was loaded onto a transport
arrangement consisting of four prime
movers pulling two 14-axle modular trailers
with the turbine loaded on a beam-set
arranged between the two trailers.
The overall length of this transport system
was approximately 110m. It moved to site
under Traffic for NSW and NSW Police
escorts between midnight and 04:00 to
minimise the impact on other traffic users.