Major projects
South Africa
Gautrain
Murray & Roberts plays a lead role in
the Gautrain Rapid Rail Link project,
which has been underway for almost
two years following commercial close
in September 2006. Civil design and
construction work is 45% complete
and detailed designs for electrical
and mechanical systems are ready
for implementation. Construction of
viaduct bridges commenced during
the year and the state-of-art tunnel
boring machine commenced tunneling
from Rosebank towards Park
|
Centre: Tunnelling equipment
at Sandton South Shaft
Top right: Train maintenance
workshop at Midrand depot
Above: Precast yard – viaduct
segments and bridge beams |
Station
in January 2008. Work in this section
is progressing to schedule, while
construction of the section north of the
Midrand Depot towards Pretoria has
been delayed by late expropriation and
release of land.
The airport link from Marlboro Portal
to OR Tambo International Airport has
also been delayed by unmapped utilities, late release of land and late approval of
access to Airports Company South Africa
(ACSA) property.
The Bombela Consortium has entered
formal negotiations with Gauteng
Province to resolve the consequence of
these issues and to agree measures for
accelerating completion of Phase 1 in
time for the 2010 Soccer World Cup.
Major projects such as Gautrain,
Green Point Stadium and the Power
Stations demand higher levels of
management focus than normal
construction activities and require a
premium allocation of skilled resources.
Murray & Roberts has adopted a
management model that ring-fences
these projects under parallel Corporate
leadership, which in the South
African context is the responsibility of
Murray & Roberts executive director
Sean Flanagan.
Green Point Stadium
The Green Point Stadium project for
the 2010 Soccer World Cup has been
underway for 18 months since award
in March 2007. Construction work is
proceeding well on this 68 000 seater
stadium and the project is on track
to commence erection of the cable
tensioned steel and glazed roof in
September 2008.
The original 34 month construction
period was reduced to 31 months at the
request of FIFA, which has subsequently
been challenged by ongoing design
changes and abnormally inclement
weather conditions.
|
Department of Foreign Affairs building
|
Work is underway on the R1,3 billion head office complex for the Department of Foreign Affairs in Pretoria. The R1,3 billion structure topped out in August and Concor is scheduled to complete the project in May 2009 |
|
Lusip Dam
|
Concor, in joint venture with Group 5 and Swaziland-based Inyatsi Construction, has successfully completed the upstream components of the LUSI P Dam Project in Swaziland |
|
Thermal Power Stations
Murray & Roberts has secured the
contracts for boiler erection and
fabrication for the Medupi and Kusile
(previously Project Bravo) coal-fired power
stations in partnership with Hitachi Power.
The Medupi contract was signed in
November 2007 and work commenced
immediately on resourcing a management
team and securing major subcontractors.
The primary contract is a partnership
between Murray & Roberts MEI and
Murray & Roberts Engineering Solutions,
with fabrication of the structural
steelwork by Genrec. Steel ducting
will be fabricated in a new facility to be
established on site by a new company
jointly owned by Murray & Roberts MEI
and a 51% empowerment partner
The Kusile contract was awarded
in January 2008 and work has
commenced on resourcing a
management team and securing major
subcontractors.
These contracts are collectively valued
at R15 billion and will take up to six
years to complete.
Murray & Roberts Construction
secured the lead contractor role in joint
venture with Concor and Grinaker LTA,
for civil construction work on the Medupi
power station. Under the leadership
of project manager Coenie Vermaak
about 170 management and senior
staff resources have been mobilised
and a total staff complement of 2 800
will be on site by the end of 2008. First
structural concrete was placed in July
2008. The contract is valued at about
R3 billion and although scheduled for
completion in 2012, progress is currently
impeded by numerous design changes
and access problems.
Civil work for the Kusile Power Station
is out for selected tender and Murray
& Roberts is well positioned to secure
further work on the proposed Open Cycle
Gas Turbine (OCGT) and the revised
Mmamabule Power Station in Botswana. |
|